Ethane Pipeline - Civils
Client: Ineos
Value: £9.9m
Project Description:
To construct in-situ piled supported reinforced concrete foundations to carry the new elevated Ethane pipes.
Works Included:
- Hand excavation to expose underground services
- Demolition of underground buried concrete structures, redundant pipes and manholes
- Hand excavation to all pre-piling to a depth of 1200mm probing to a full depth of 2m
- All areas consisting of holding down bolts and grouting to base plates
- Construction of access roads, hard standings, piling mats and footpaths
- Construction of transformer pens, outstation slabs, valve access platforms
- Construction of reinforced pile caps and pipe sleepers
Photo Gallery
Click on image to view full screen