Enhanced Gas Separation Project
Client: BP FPS Kinneil
Value: £10m
Project Description:
Enabling and new civils infrastructure for Enhanced Gas Separation Project and supply network.
Works Included:
New Trains 1 & 2 Exchangers (KA23)
- Enabling Works to construct new service routes to allow the diversion of safety critical and process critical services.
- Carried out works to divert existing GRP Firemain to allow follow on construction works
- Installation of 72no Driven Concrete Piles
- Installation of various concrete pile caps, columns and slabs for new PAU's to be assembled upon.
- Installation and construction of road modifications and temporary hardstandings to facilitate the heavy haul routes for PAU delivery
Crude Oil Stabilisation (KA31)
- Installation of 12no Mini Ishebek Piles
- Installation of Concrete Pilecaps and support structures
- Construction of New Culvert to 3rd Street
Crude Oil Stabilisation (KA24)
- Removal and disinvestment of existing buried structures, including 50no existing concrete piles
- Removal of contaminated drainage and pipe bedding materials and reinstatement of lines
- Installation of 150no concrete driven piles
- Installation of various concrete pilecaps, support structures, pipe rack foundations, high point paving and roads
- Installation of new surface water and oily water drainage systems using cement lined ductile iron, concrete and vitrified clay pipes
- Construction of insitu concrete manholes
Cooling Water Package (KA24)
- Installation of 50no concrete driven piles
- Construction of cooling tower structure (base 200m3 concrete), plus 2.5m high concrete walls to the perimeter
- Installation of 20" valve and pipe feeds for cooling tower
Transformers (KA45)
- Construction of 2no transformer pens
- Excavation and construction of 240m service trench to feed transformers
- Construction of various concrete structures to take UPS buildings
During the course of the works we have also installed approx 4000m² of external concrete hardstandings for use by the mechanical contractor to fabricate his works upon, including the raft foundations to the construction village and heavy plant haul roads